SECTOR
Producer of raw phosphate, phosphoric acid and phosphate fertilizers.
Producer of raw phosphate, phosphoric acid and phosphate fertilizers.
Jorf Lasfar, El Jadida, Morocco
Our customer launched a major investment programme to expand its production site. The project consisted of the construction of two DAP (diammonium phosphate) fertilizer factories with a total production capacity of 1.7 million tonnes/year.
The project also included conveyor systems and zones for acid storage tanks.
Following a quarterly visit to our customer in Casablanca, we learnt about the launch of his extension project.
Through our customer and our local network, we contacted the boiler making company (the contractor) who would take care of the supply and the assembly on site.
The contractor visited the Managing Director, the Project Manager and the Purchasing Manager to introduce VM and organise a meeting.
We submitted our offer.
Negotiation, award and fine-tuning of the final technical and logistical details.
In continuous communication with the customer in order to deliver the materials over 12 months with very precise "time points".
On-site visit to observe the proper execution of the supply.
Grade |
Products |
Specifications/Standards/Comments |
316L |
Tubes, flanges & accessories |
Welded and seamless tubes according to ASTM A312, ASME B36.19, Flanges according to ASTM A182 Accessories according to ASTM A403
|
904L |
Tubes, flanges & accessories |
Tubes, flanges & accessories Welded tubes according to ASTM A312 with 100% radiography of the welds Seamless tubes according to ASTM A312, ASME B36.19, Flanges according to ASTM A182 Welded accessories according to ASTM A403 with 100% radiography of the welds Seamless accessories according to ASTM A403
|
In the sector of phosphoric acid and fertiliser production, the quality of the steel products is paramount.
VM Steel supplied high-quality materials and all the necessary materials certificates that testify to this quality, in compliance with the most restrictive international standards.
The specifications for such a project obliged us to respect the agreed delivery times scrupulously.
Our logistics department worked closely with the transporters and our customer to respect these very short delivery times spread over a whole year.
Deliveries spread over 12 months